A new Louvre museum is emerging on reclaimed land on the edge of the Persian Gulf. It’s one of a number of architectural mega-projects transforming oil-rich states in the Middle East.

On an early summer morning, downtown Abu Dhabi doesn’t so much shimmer in the desert heat as swelter.

In near-100 degrees Fahrenheit (38 degrees Celsius), skyscrapers set back from the city’s corniche loom over the edge of the Persian Gulf, modern monuments to the Emirate’s oil-fuelled wealth.

lad_chapter2_1120

If the gleaming buildings represent the transformation of the United Arab Emirates over the last fifty years, what’s emerging just a ten-minute drive away on Saadiyat Island is a vision of what the Gulf state hopes will be a marker for its future.

Today, it’s mostly a vast construction site – nothing new for this booming country – but covering 27 square miles, the island is steadily being transformed into a cultural hub with high-end resorts and homes that the government hopes will make the world sit up and take notice.

Home already to a campus for New York University, it will soon be joined by three major international museums, including what will be the world’s largest Guggenheim museum (designed by Frank Gehry), and, opening next year, a new Louvre.

Designs by architects Ateliers Jean Nouvel suggest the Louvre structure will look every bit as eye-catching as anything displayed inside it.

lad_chapter8_1120

Yet the setting couldn’t be more different from the heart of Paris, where the world’s most-visited museum has stood for centuries.

On partly reclaimed land jutting into emerald waters, eight cranes tower over the main structure, where each day thousands of construction workers and 250 managers and architects are racing to complete the building for a December 2015 opening.

Amer Kharbush, the project manager from Turner Construction, is responsible for marshaling the effort to keep the construction on track.

Stepping out of an air-conditioned SUV onto the site, the UAE resident by way of Florida takes stock of what they’ve achieved since work began in January 2013.

“This is unique,” he says, proudly surveying the half-completed structure.

“The teamwork, from the contractors to the engineers: People really want this job to be built. I mean, how many Louvres do you get to build in a lifetime?”

Those creating the first Louvre museum for centuries might feel the weight of history upon them, but the modern challenges are just as sizable for Kharbush and co.

lad_graphic1_640

The finished museum will really be 47 buildings made to look like one, with no two walls the same.

Its most striking feature will be a vast steel dome that will create a “rain of light” effect on the visitors walking below. Through a latticework, the roof will be pierced by sunlight, illuminating areas below, reminiscent of the dappled light of semi-covered traditional Arab souks.

Building the roof takes 85 unique substantial elements, each weighing up to 75 tons and covered by eight layers of cladding.

When complete, the steel alone will weigh as much as the Eiffel Tower, while the cladding on the 180-meter-diameter dome will help tip the scales at 12,000 tons.

“When we lifted the first piece of the dome, it was like a celebration,” says Kharbush.

“Of course it was a milestone, but it took a couple of weeks to take that first piece and place it. The first piece is the most important.”

While a forest of steel supporting structures currently fills the space under the dome, they will be removed when it’s complete. The enormous flying-saucer-shaped dome will then become airborne: lifted up as one piece by giant cranes to be placed on just four huge concrete piers.

The one-off nature of the project is reflected elsewhere in the structure: No two of the 4,000 concrete panels covering the building are the same.

Each has to be made individually and “cured” with enhancing chemicals for 28 days.

“You can’t have any of them out by a millimeter,” says Kharbush.

“You’ve got 145,000 cubic meters of concrete, over 7,000 tons of steel, 5,000 tons of cladding, you look at this thing and it’s massive; it’s beautiful.”

If the beauty for the engineering team often lies in the unseen details, ten architects from Jean Nouvel’s firm are on-site to ensure the building stays exactly to the specified design.

Pritzker Prize-winner Nouvel initially designed the building simply as a classical art museum.

“I found it to be a wonderful coincidence that it was to be the Louvre and not any other international museum,” says Nouvel.

“I was proud to be, in a way, ‘the architect of the Louvre.'”

“Above all, I wanted to ensure that this museum belongs to local, Arab, Islamic cultural heritage by employing symbols such as the domes or other archetypes. I also took into account the local climate.”

The daily routine for architects involves morning meetings with the contractors who are in charge of each element of the structure. The architects are presented with drawings of what is being done to ensure there are no mistakes or deviations from the client-approved plans.

From paint and light bulbs to concrete panels, nearly every part of the museum is carefully tested, much of it in a specially built on-site test center, a mini version of the finished building, itself seven stories tall and located just a few hundred meters from the main construction site.

A workman on the site of the Louvre Abu Dhabi.

“The site work is extremely dense,” says Paris-based Hala Warde, the lead architect from Ateliers Jean Nouvel, who heads the team. As well as the structure, she and her team have designed many of the features within the museum, including furniture and fixtures.

That includes the window blinds, skirting boards and different wall finishes.

“What’s taking so much of our time is working on a mock-up that captures every little detail that we have within the building,” she said.

When the museum is complete, a large part of the land surrounding the site will be flooded, leaving the structure seemingly floating in the sparkling waters of the Gulf, while a number of tidal pools will be created “inside” the building, under cover of the vast dome.

Visitors will be able to stroll through the gallery and enjoy a view from the café across the water towards the other museums that will take shape on the island, yet few will have an inkling of what will be below their feet.

“This is really just the tip of the iceberg,” says Kharbush of the gallery space. “There’s a city under here, of tunnels, bathrooms, kitchens; that’s what’ll keep it alive.”

While out of sight, this subterranean labyrinth, nine meters below sea level, is getting just as much careful attention from the builders as the eye-popping architectural elements above.

“Water is even worse than fire in a museum,” says Kharbush. “No water is coming into this building, ever!”

To ensure the building is watertight, two layers of high-tech waterproofing have been tested to the limits.

There are fail-safes in place, too, should a leak appear. Two layers of rubber that expand on contact with water have been built in, while between the two outer waterproof membranes there is a miniscule chamber than can be injected with grout via a system of pipes and electronically controlled hoses. The whole system is wired up so a leak can be located and fixed as soon as it springs.

Rest areas provide constructions workers with a refuge from scorching summer temperatures.

The green covering, just millimeters thick, will clad the 760 underwater panels of the building, while test panels were submerged for months to ensure that they were fit for purpose.

Engineers have also constructed off-shore breakwaters to lessen the power of the waves that will lap against the building and bring water into the museum’s series of channels, inspired by traditional Arab “falaj” water systems.

If avoiding damage to the pieces of irreplaceable art is essential, so too is security.

Before more high-tech measures are wired in to protect the art from any attempted heists, security starts with the design of the underground tunnels.

Yet the secrecy surrounding the security measures is so tight that only a handful of people working on the project know anything about it.

“The tunnels will link all the museums. It’s a security strategy and there’s only two or three on the site who know about (the security set-up) and they’ve each signed a non-disclosure agreement.”

Rising ambition: When completed the dome will be the iconic element of the gallery.

Which means Al Hammadi can’t say any more about it, although others working on the project suggest that even he is probably only party to some, not all, of the security measures, from the tunnels to the surveillance cameras and alarms, being worked into the building.

If the anti-theft measures will be unseen, currently most of the constructions workers are, too. The majority of the work is going on inside the structure.

During summer months, work outside stops during the hottest hours from 11am to 3pm, when temperatures soar above 118 degrees Fahrenheit (42 degrees Celsius).

Aside from the break, construction continues around the clock, with shift work the norm, seven days a week aside from Friday afternoons to accommodate the Muslim observance of Friday prayers.

When the “finishing” part of the Louvre’s construction begins, around 7,000 laborers will work on site.

Hailing mainly from countries across south Asia, the working conditions of the men who physically create the big and bold markers of the 21st century have long been in the spotlight.

The reports earlier in 2014 of labor abuses during the construction of the nearby campus for New York University (NYU) are being investigated by the UAE government via an independent investigation firm.

In a statement to the NYU community after the NYT report about working conditions, university president, John Sexton, called workers’ treatment “if true as reported, troubling and unacceptable,” and “out of line with the labor standards we deliberately set for those constructing the ‘turn-key’ campus being built for us on Saadiyat Island and inconsistent with what we understood to be happening on the ground for those workers.” The statement goes on to say: “We will be working with our Abu Dhabi partners to investigate these reports vigorously.”

There have not been any allegations of labor abuses made against the Louvre.

When asked about the treatment of workers, the Tourism Development and Investment Company (TDIC), the government-backed master planner and developer of all the projects on Saadiyat Island, told CNN it takes worker welfare very seriously.

It’s keen to point out that an Employment Practices Policy that goes beyond those mandated by UAE law and applies to all projects on Saadiyat Island has been in place since 2009, while it commissioned PricewaterhouseCoopers to run an independent audit on working and living conditions on Saadiyat Island.

The 2013 report highlighted improvements, but still found cases of workers paying recruitment fees and some of having their passports confiscated for months, in contravention of the UAE’s labor laws.

There are hundreds of companies across the Middle East involved in the supply and hiring of migrant workers. From fixers in migrant workers’ home countries who assist them in finding jobs, to contractors and sub-contractors at their destination, the process can be complex and involve numerous parties.

Welfare groups like Human Rights Watch often highlight the potential for abuse where “kafala” – a system of employment whereby a foreign worker must be sponsored by a local citizen or employer – is used. The system places legal responsibility for employees with the employer. It has been criticized for instilling employers with a sense of “ownership” and leaving workers with little chance to change jobs or returning home. There have been cases where some employers ignore the law, withhold wages and confiscate workers’ passports.

For Kharbush, safety on the site is always the most important factor. As well as ensuring best practice in that regard, every hour to 90 minutes the workers take a ten-minute water break.

During the punishing heat of summer, many take refuge from the scorching sun and humidity at rest areas and sit among the freshly dried concrete, where in 15 months, priceless art works will take their place.

If the dome of the Louvre represents just the tip of the development iceberg transforming Saadiyat, the island itself is just one of many billion-dollar mega-projects — from new airports to the next world’s tallest building — transforming the UAE and neighboring countries.

Each in its own way is pushing the boundaries of what can be built, feeding into the desire for governments to promote their countries as global hubs for investment, leisure and business.

The right to host the 2022 World Cup has given resource-rich Qatar impetus to invest in flagship projects such as a high-speed rail network as well as its futuristic football stadia and the recently opened Hamad International Airport.

Last year, $58 billion was spent in Qatar on infrastructure projects, on top of an existing $128 billion, according to Ventures Middle East, a Middle-East-focused strategic business consultancy that counts Microsoft, LG and Audi among its clients.

Saudi Arabia is also championing its own mega-projects, with a huge urban metro system planned for the car-loving capital Riyadh, while in Jeddah the plans are in place for what will be the world’s tallest building, the Kingdom Tower.

But if one location in the Gulf region is the poster boy for building big, it’s Dubai.

The Burj Khalifa – all 163 stories of it – pierces the city’s sky and manages to make nearby 50-story towers seem diminutive. Little here appears built on a human scale and the quest for superlatives is the norm: The world’s most-visited shopping attraction (the Dubai Mall), the world’s tallest building, the world’s highest fountain …

Nobody does it bigger: Construction continues apace in Dubai.

If the 2009 global financial crisis caused many projects in the Emirate to stall, new rules and consolidation of developers over the last few years have seen construction continue apace. Government figures from 2012 show that over 467,000 people were working in the construction industry in Dubai; the population is around 2.2 million.

According to Ventures Middle East, construction contracts for 2015 are projected to be around $50 billion, almost double what they were two years ago.

Dubai will host Expo 2020, which will fill in a huge swath of the desert near the new Al Maktoum airport, and many developers have seen it as a boost to other projects and investment in the city.

For Paul Lagan, a project director with Keo International Consultants, the biggest challenge to construction in Dubai and the region isn’t the ambition of the design or the size of the project, but time.

“It’s not unusual for the designs to be incomplete before the construction begins,” he says on the building site of the Paramount Towers in Dubai’s Business Bay.

And that’s the reality of the commercial side of the construction business: Getting things made to tight deadlines to get the capital flowing in.

Some believe this could be the high point for the Middle East’s mega-projects.

“Many projects were either planned or started pre-financial slow-down in 2008, and we’ll see less being announced now,” says Mibu John, research director for Ventures Middle East.

While many of the projects have a spectacular element, like Dubai’s Expo or Qatar’s World Cup plans, many are part of government plans to diversify their economies and address real needs like more housing.

Of course, there is still an element of keeping up with the neighbors.

“In the UAE, you can see that the things done in Dubai and Abu Dhabi complement each other: Saadiyat being a cultural hub to go with Dubai’s huge growth in tourism,” says John.

“But these countries are looking at what each other are doing and seeing what better they can do.”

Back on the site of the Louvre, Kharbush remains focused on the all-consuming job that will keep him occupied until the end of 2015.

The soon-to-be-delivered fleet of “crawler cranes” – each able to lift 1,600 tons and take 70 trucks to move – are the latest thing to excite him about the project. To add another superlative to the project, they’re the largest of their kind in the world and will be used to lift the dome, once complete, as a single piece.

But even among the ceaseless activity, Kharbush can find a few moments for reflection and absorb the enormity of this once-in-a-lifetime project

“This is one of the favorite parts of the project for me,” he says, standing on the bare concrete of what will become the museum’s café.

“People when they come are going to look at the view from here, but you’ll be nearest to the dome when it’s finished. For us engineers who are actually part of the project, we know what it took to construct this and we get a special feeling.”

“The entire world is looking at this job when it’s done, it’s going to be everywhere. So everything about it just has to be immaculate.”

Producer: Dean Irvine; Editor: Linnie Rawlinson; Design: Inez Torre; Development: Nav Garcha
Cover images: Courtesy Ateliers Jean Nouvel, Artefactory, TDIC, Louvre Abu Dhabi

Read more at CNN

Advertisements

One thought on “Building the new Louvre: Turning the desert into a cultural jewel

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s